Lydig was responsible for setting the concrete for 58 wind turbine generator foundations for the Palouse Wind Farm south of Rosalia, Washington. The project was completed in 12 weeks, with excavation quantities in excess of 90,000 bank cubic yards, the pouring of over 24,000 cubic yards of concrete, and setting of 7,192 anchor bolts.
Lydig was responsible for setting the concrete for 58 wind turbine generator foundations for the Palouse Wind Farm south of Rosalia, Washington. The project was completed in 12 weeks, with excavation quantities in excess of 90,000 bank cubic yards, the pouring of over 24,000 cubic yards of concrete, and setting of 7,192 anchor bolts.