Our wORK / Projects / Industrial / BPA Central Substation Foundation/Controls

BPA Central Substation Foundation/Controls

As a subcontractor to Wilson Construction, Lydig completed the forming of 400+ concrete foundations and placed nearly 2500 cubic yards of concrete.

BPA Central Substation Foundation/Controls
Owner

Bonneville Power Administration

Cost

Phase I: $1M (2010) Phase 2: $1.6M (2010)

This project was completed on a very aggressive schedule requiring the work to be completed in six weeks. After completion of that phase, Lydig completed the Control Building for the project which consisted of concrete foundations/slab on grade, concrete masonry unit walls, wood trusses and metal roof panels.

Recent Projects